महाराष्ट्र अभियंता सेवा (स्थापत्य) मुख्य परीक्षा २०१२ पेपर १ Questions And Answers:
Vertical limits within which cable is to be provided in a post-tensioned prestressed concrete element is called as
Minimum grade of concrete to be used for pre- and post-tension prestressed concrete construction are
The resist bursting tension, designed reinforcement is distributed in the zone of __________ from the loaded face of the end block, where 2y0, is depth of equivalent prism.
What is the correct order of increase in ultimate moment of resistance of
I. Pre-tension section
II. Post-tension bonded section
III. Post-tension unbonded section,
keeping all other parameters same.
Deflection of a simply supported prestressed concrete beam of span 'V and flexural rigidity 'EI', due to a straight cable carrying prestressing force 'P' and eccentricity 'e' below the neutral axis is
A cantilever beam of span 'L' is supporting a udl of intensity 'w'. Most suitable cable profile will be
The shortcoming of bar chart is
Among the following, who is considered as the father of scientific management ?
Program Evaluation and Review Technique is used when
Which of the following is the main contribution of scientific management ?
The sequence to be followed while developing the network diagram is
a. defining objectives
b. sequencing the activities
c. breaking down the structure
d. developing the relation between events
In what way does ABC analysis help the manager ?
The optimistic time, pessimistic time and most likely time required for completion of activity is 4, 11 and 6 days respectively. The expected time is
Which of the following is the formula for Economic Order Quantity if M is annual demand, Co, is ordering cost, Cc, is inventory carrying cost and S is unit price of an item ?
The optimistic time, pessimistic time and most likely time required for completion of an activity is 4, 8 and 6 days respectively. The variance of time estimate is
Which of the following Acts specially covers safety legislation of construction industry in India ?
Most of the accidents in construction industry happen due to
CPM network is
The fire safety requirements of the building are designed as per
Optimum duration of project corresponds to which of the following ?
आता मिळवा सर्व जाहिराती Telegram Channel वर (अगदी मोफत) - येथे क्लिक करा
Maha NMK Here You will get the list of all district from Maharashtra. You Can Select Any Disctrict From The List And Get Latest Recruitment News For The District. Keep Visiting MahaNMK Daily For The Latest Recruitment new and Free Job Alert
© Maha NMK™ | Copyright 2015 - 2023 All Rights Reserved.
Made with ❤ in India.